Washington Suburban Sanitary Commission
WSSC operates and maintains two water reservoirs with
a combined capacity of 14 billion gallons; two water
filtration plants that produce an average of 167 million
gallons of clean water per day; 14 water pumping stations;
six wastewater treatment plants; and 43 wastewater pumping
stations. The infrastructure includes 10,200 miles of
water and sewer mains. With an operating budget of $494
million, WSSC is among the 10 largest water and wastewater
utilities in the nation.
WSSC contracted with Constellation Energy's Projects &
Services Group (CEPS) to reduce its energy and operational
costs while increasing energy and operational efficiencies
to meet the challenges of future demand. CEPS had to
meet strict fiscal goals. The $10 million capital project
would have to be self-funded. To ensure a positive cash
flow, CEPS would have to capitalize on energy and operational
savings while assisting WSSC in obtaining low-cost financing.
CEPS identified numerous energy conservation measures
and technological solutions that would maximize energy
and cost savings as well as achieve operational and
maintenance savings. The CEPS audit also revealed that
to use energy as efficiently as possible, WSSC would
have to buy it as efficiently as possible. That meant
purchasing competitively priced electricity on the open
market. CEPS’s expertise in providing competitive
electrical supply enabled WSSC to take full advantage
of the deregulated energy marketplace.
WSSC systems were upgraded to both improve operational
efficiencies and enhance the ability to procure competitive
electric supply. CEPS then worked with WSSC to determine
its balance of risk tolerance and budget certainty as
it developed the supply strategy for both electric capacity
and energy purchases. Then, CEPS competitively procured
about 24 MW of generation capacity and more than 165,000,000
kWh of electricity with the balance supplied through
the real-time markets. This agreement covers billing
services and supplier account management over a five-year
period at 22 facilities responsible for approximately
95 percent of WSSC’s overall electrical usage.
To complement the capital project implementation and
commodity arrangement, on-going active load management
services through peak shaving, load shaping and distributed
generation are integrated into the supply-side procurement
strategy. This further enhances the risk management
function and the coordination of energy blocks and capacity
bids. The next phase of project implementation includes
reduction of natural gas usage, expansion of distributed
generation, improvement of incinerator operations and
further reduction of electrical usage.
CEPS successfully delivered on a long term project with
guaranteed savings, competitively priced energy supply,
efficient operations, reduced maintenance costs, increased
reliability, and an upgraded infrastructure to meet
energy demand for decades to come. To WSSC and its customers,
inviting CEPS to prepare the way for future growth was
a watershed event.
Operational savings from the $10 million capital project
exceeded the project funding payments. CEPS assisted
WSSC in obtaining long-term, low-interest financing
through the State of Maryland’s Water Quality
Revolving Loan Fund Program.
|